SWOT Analysis for Risk Identification
PMBOK v8 Definition
SWOT analysis is the analysis of strengths, weaknesses, opportunities, and threats of an organization, project, or option. For risk identification, it is used to increase the breadth of identified risks by including internally generated risks. The technique starts with the identification of strengths and weaknesses of the organization, focusing on either the project, organization, or the business area in general. SWOT analysis then identifies any opportunities for the project that may arise from strengths, and any threats resulting from weaknesses. The analysis also examines the degree to which organizational strengths may offset threats and determines if weaknesses might hinder opportunities.
Why It Matters for the Exam
This concept appears frequently in PMI exam questions about risk identification tools and techniques. You will encounter it in situational questions asking which technique to use when the team needs to analyze internal factors to broaden risk identification, or in definition-based questions asking about the specific purpose and components of SWOT analysis.
Key Points to Remember (for the exam)
- Primary Purpose: Increases the breadth of identified risks by including internally generated risks
- Starting Point: Identification of strengths and weaknesses of the organization
- Scope Options: Can focus on the project, organization, or business area in general
- Four Components: Strengths, Weaknesses, Opportunities, Threats
- Key Analysis: Examines how strengths can offset threats and whether weaknesses might hinder opportunities
- Risk Identification Tool: Used specifically within the Identify Risks process
- Internal vs External: Strengths and weaknesses are internal; opportunities and threats are external
Typical PMI Exam Example
A project manager is leading a risk identification workshop for a new product development project. The team wants to ensure they capture risks arising from the organization's internal capabilities and limitations. Which technique should the project manager use? The correct answer is SWOT analysis, as it starts with identifying organizational strengths and weaknesses (internal factors) and then identifies opportunities and threats (external factors).
PMI Exam Traps
-
Trap: Confusing SWOT analysis with a general strategic planning tool only Reality: In PMBOK v8, SWOT analysis is specifically used for risk identification to increase the breadth of identified risks
-
Trap: Thinking SWOT analysis only identifies threats Reality: SWOT analysis identifies both opportunities (from strengths) and threats (from weaknesses), plus examines their interactions
-
Trap: Believing SWOT analysis focuses only on the project level Reality: SWOT analysis can focus on the project, organization, or business area in general
-
Trap: Confusing SWOT analysis with other risk identification techniques Reality: SWOT analysis is unique because it starts with internal analysis (strengths/weaknesses) before moving to external factors (opportunities/threats)
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Risk Identification | Process where used | SWOT analysis is a tool and technique in the Identify Risks process |
| Risk Register | Output | Risks identified through SWOT analysis are documented in the risk register |
| Organizational Structure | Input consideration | SWOT analysis examines organizational strengths/weaknesses, which relate to structure |
| Contingency Reserve | Related strategy | Active acceptance strategy establishes contingency reserves for threats identified via SWOT |
Quick Review Questions
-
What is the primary purpose of using SWOT analysis in risk identification?
-
What are the four components of a SWOT analysis?
-
When conducting a SWOT analysis, what is the starting point according to PMBOK v8?
-
How does SWOT analysis examine the relationship between strengths and threats?
-
On what levels can SWOT analysis focus (project, organization, or business area)?
PMBOK v8 Reference
Section 11.2 - Identify Risks (Tools and Techniques: SWOT Analysis)