Planning, Executing, and Monitoring Focus Areas: Core Project Management Activities
PMBOK v8 Definition
The Planning Focus Area involves developing the project management plan and its subsidiary plans to establish the scope, schedule, budget, and approach for delivering project outcomes. The Executing Focus Area focuses on completing the work defined in the project management plan to meet project objectives. The Monitoring and Controlling Focus Area tracks, reviews, and regulates project progress and performance, identifying any areas where changes to the plan are required. These three focus areas are performed iteratively and in parallel throughout the project life cycle.
Why It Matters for the Exam
The PMI exam frequently tests the distinction between Planning, Executing, and Monitoring and Controlling activities, especially in situational questions where you must identify which focus area is being performed. Questions often present a scenario and ask whether the project manager is planning, executing, or monitoring/controlling, or which output belongs to which focus area.
Key Points to Remember (for the exam)
- Planning Focus Area Output: The project management plan and all subsidiary plans (scope, schedule, cost, quality, etc.)
- Executing Focus Area Output: Deliverables, work performance data, change requests, and project team assignments
- Monitoring and Controlling Focus Area Output: Work performance information, change requests, and project documents updates
- Parallel Execution: Monitoring and Controlling is performed in parallel with the other focus areas-it is not a separate, stand-alone area
- Corrective Actions: Monitoring and Controlling identifies corrective actions, which are then negotiated and agreed upon by appropriate stakeholders
- Consistency of Effort: For projects with a stable project management plan, Monitoring and Controlling effort is fairly consistent throughout execution
- Adaptive Projects: For projects undergoing frequent and significant changes (common with adaptive approaches), Monitoring and Controlling efforts are likely to be less consistent
Typical PMI Exam Example
A project manager is reviewing the project schedule and comparing actual start dates to planned start dates. She notices a two-week delay and calculates the schedule variance. She then documents this information and prepares a change request to adjust the project plan. Which focus area is the project manager performing?
Answer: Monitoring and Controlling Focus Area (tracking performance, identifying variances, and recommending corrective actions)
PMI Exam Traps
-
Trap: Thinking Planning only happens at the beginning of the project
-
Reality: Planning is iterative and occurs throughout the project life cycle, especially when changes are approved
-
Trap: Confusing work performance data with work performance information
-
Reality: Work performance data (raw data) is an output of Executing; work performance information (analyzed data) is an output of Monitoring and Controlling
-
Trap: Believing Monitoring and Controlling is a separate phase that starts after Executing
-
Reality: Monitoring and Controlling is performed in parallel with all other focus areas, including Planning and Executing
-
Trap: Assuming all corrective actions are implemented immediately
-
Reality: Corrective actions identified during Monitoring and Controlling must be negotiated and agreed upon by appropriate stakeholders before implementation
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Project Management Plan | Input to Executing and Monitoring | The plan guides all execution and monitoring activities |
| Work Performance Data | Output of Executing | Becomes input to Monitoring and Controlling |
| Work Performance Information | Output of Monitoring | Used for performance reporting and decision-making |
| Change Requests | Output of both Executing and Monitoring | Distinguish between corrective actions (Monitoring) vs. defect repairs (Executing) |
| Project Life Cycle | Framework for Focus Areas | Planning, Executing, and Monitoring occur within each phase of the life cycle |
Quick Review Questions
-
A project manager is developing the schedule management plan and defining activities. Which focus area is being performed?
-
During project execution, the team completes several deliverables and records the actual hours worked. What type of output is this?
-
The project manager notices that the actual cost is exceeding the planned budget by 15%. She analyzes the variance and prepares a recommended corrective action. Which focus area is she performing?
-
For a project using an adaptive approach, how does the Monitoring and Controlling effort differ from a predictive approach project?
-
After identifying a corrective action during Monitoring and Controlling, what must happen before it can be implemented?
PMBOK v8 Reference
Section 4.5.2 - Planning Focus Area
Section 4.5.3 - Executing Focus Area
Section 4.5.4 - Monitoring and Controlling Focus Area
Section 4.5.6 - Focus Areas as a Whole