
The Tailoring Process: Four Steps for Project Adaptation
PMBOK v8 Definition
Tailoring is the deliberate adaptation of project management approaches, governance, and processes to fit the specific context, environment, and characteristics of a project. The tailoring process consists of four sequential steps: selecting an initial approach, tailoring for the organization, tailoring for the project, and implementing ongoing improvement, as shown in Figure 3-3. Prior to tailoring, the project environment should be thoroughly analyzed and understood.
Why It Matters for the Exam
The PMI exam frequently tests tailoring because it represents a core PMBOK v8 principle: no two projects are identical, and rigid application of standard processes leads to failure. Expect situational questions where you must identify which tailoring step is being performed or which tailoring suggestion applies to a specific project problem, particularly in scenario-based questions about adapting processes to unique project environments.
Key Points to Remember (for the exam)
-
Four Sequential Steps: (1) Select Initial Development Approach, (2) Tailor for the Organization, (3) Tailor for the Project, (4) Implement Ongoing Improvement. This order is fixed and tested.
-
Step 1 – Select Initial Approach: Project teams apply knowledge of the product, delivery cadence, and available options to choose predictive, adaptive, or hybrid development approach best suited for the endeavor.
-
Step 2 – Tailor for the Organization: Modify the selected approach based on organizational requirements, policies, practices, and procedures.
-
Step 3 – Tailor for the Project: Adjust based on size, criticality, and other project-specific factors. This is where performance domains are tailored based on project uniqueness.
-
Step 4 – Implement Ongoing Improvement: Inspect and adapt the tailored approach continuously throughout the project lifecycle.
-
Common Situations Table (Table 3-1): When deliverables are poor quality, analyze root causes and implement targeted feedback and quality assurance measures, focusing on process improvements rather than just increasing verification steps.
-
Common Confusion: "Tailoring for the Organization" vs. "Tailoring for the Project" – The organization step addresses enterprise-level constraints (policies, standards), while the project step addresses project-specific factors (size, criticality, complexity).
-
Tailoring Considerations: These should be applied to corresponding project management activities to ensure alignment with project objectives, even if those activities are defined per policies, practices, or procedures.
Typical PMI Exam Example
A project manager is assigned to a new software development project in an organization with strict regulatory compliance requirements. The team is experienced with agile methods. The project manager first selects an adaptive approach, then modifies it to incorporate regulatory gate reviews (organizational tailoring), then adjusts sprint length based on project complexity (project tailoring), and finally establishes retrospectives to continuously improve the process. This demonstrates the correct sequence of the four tailoring steps.
PMI Exam Traps
-
Trap: Confusing "Select Initial Development Approach" with "Tailor for the Organization"
-
Reality: Selection comes first; organizational tailoring modifies the selected approach based on enterprise constraints
-
Trap: Thinking tailoring is a one-time activity at project start
-
Reality: Step 4 requires ongoing improvement throughout the project lifecycle
-
Trap: Applying standard verification steps when quality is poor
-
Reality: PMBOK v8 says focus on process improvements and root cause analysis, not just increasing verification
-
Trap: Confusing tailoring with customization of deliverables
-
Reality: Tailoring adapts the project management approach, processes, and governance—not the product itself
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Development Approaches (Predictive, Adaptive, Hybrid) | Input to Step 1 | Exam tests which approach fits which project context |
| Performance Domains | Tailored in Step 3 | Each domain's work can be tailored based on project uniqueness |
| Project Management Focus Areas (Initiating, Planning, Executing, M&C, Closing) | Affected by tailoring | Tailoring considerations apply to all focus area activities |
| Organizational Policies & Procedures | Constraint in Step 2 | Organizational tailoring ensures alignment with existing requirements |
Quick Review Questions
-
What are the four steps of the tailoring process, in the correct order?
-
A project team notices that deliverables consistently have quality issues. According to Table 3-1, what is the recommended tailoring suggestion?
-
What must occur BEFORE tailoring begins, according to PMBOK v8?
-
During which tailoring step does the project team select between predictive, adaptive, or hybrid development approaches?
-
What is the difference between tailoring for the organization (Step 2) and tailoring for the project (Step 3)?
PMBOK v8 Reference
Section 3 – Tailoring (pages 105-112)
Figure 3-1: The Tailoring Process Overview
Figure 3-3: The Tailoring Process
Table 3-1: Common Situations and Tailoring Suggestions