The Successful Completion Moves Organization to Future State
PMBOK v8 Definition
The successful completion of a project results in the organization moving to the future state and achieving value for the organization, as defined by key stakeholders. From a business perspective, a project’s purpose is to move an organization from one state to another to achieve a specific objective. Before the project begins, an organization is in its current state. The desired result of the change driven by the project is described as the future state. For some projects, this shift may involve creating a transition state where several steps are taken in a structured manner to achieve the future state.
Why It Matters for the Exam
This concept appears frequently in PMI exam questions about project purpose, value delivery, and stakeholder alignment. You will see it in situational questions asking why a project was initiated, what defines project success, and how value is measured. Questions often test whether you understand that projects are change drivers—not just task completions—and that success is measured by achieving the future state defined by key stakeholders.
Key Points to Remember (for the exam)
- Core Purpose: A project’s purpose is to move an organization from current state to future state to achieve a specific objective
- Three States: Current state → (possible) Transition state → Future state
- Value Definition: Value is defined by key stakeholders, not by the project team alone
- Success Dimensions: Two dimensions assessed—success of project outcomes AND success of project management processes
- Outcome Focus: The first dimension (outcomes) focuses on effectiveness in realizing intended value
- Alignment Requirement: Projects are only authorized when aligned with the organization’s strategic objectives
- Business Case Link: Business case enables stakeholder alignment on priorities and constraints from the start
Typical PMI Exam Example
A manufacturing company initiates a project to implement a new inventory management system. The current state involves manual stock tracking with 15% error rates. The future state is automated tracking with 99% accuracy. Key stakeholders (CEO, CFO, warehouse manager) define success as reducing inventory costs by 20% within 12 months. The project team completes all deliverables on time, but inventory costs only decrease by 5%. Question: Was the project successful? Answer: No—project management processes succeeded, but project outcomes failed to achieve the intended value.
PMI Exam Traps
-
Trap: Confusing "project completion" with "project success"
- Reality: Completion means deliverables are done; success means the future state and value are achieved
-
Trap: Thinking the project manager defines value
- Reality: Value is defined by key stakeholders, as stated explicitly in PMBOK v8
-
Trap: Ignoring the transition state
- Reality: Some projects require a transition state with structured steps to reach the future state
-
Trap: Measuring only process success (on time, on budget)
- Reality: Two dimensions must be evaluated—outcome success AND process success
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Business Case | Input to Initiating | Business case enables stakeholder alignment on priorities and constraints; projects authorized only when aligned with strategic objectives |
| Project Charter | Output of Initiating | Captures the desired end state; project manager may be involved in developing business case and defining benefits |
| Stakeholder Register | Output of Initiating | Stakeholders who influence outcomes are identified; their desired engagement levels (C vs D) must be managed |
| Value Delivery | Outcome of Project | Project success requires evaluating effectiveness in realizing intended value, not just completing deliverables |
Quick Review Questions
-
A project is complete, all deliverables are accepted, and it finished under budget. However, the organization did not achieve the cost reduction promised in the business case. Has the project succeeded? Why or why not?
-
What are the three possible states an organization moves through during a project, according to PMBOK v8?
-
Who defines the value that a project must achieve upon completion?
-
A stakeholder is aware of the project and its potential impacts but is neither supportive nor unsupportive. What is their engagement level called?
-
What two dimensions must be evaluated when assessing project success?
PMBOK v8 Reference
Section 1.3 - Value Creation Through Organizational Change