
Resources Project Resource Management
PMBOK v8 Definition
Resource planning is performed to determine and identify an approach to ensuring that sufficient resources are available for the successful completion of the project. The resource control includes information on managing inventory, equipment, and supplies throughout the project life cycle. Resource requirements identify the types and quantities of resources required for each work package or activity, and can be aggregated to determine the estimated resources for each work package, each WBS branch, and the entire project.
Why It Matters for the Exam
This concept appears frequently in PMI exam questions related to the Planning and Monitoring & Controlling Process Groups. Questions test your understanding of how physical resources (equipment, materials, supplies, facilities) differ from team resources, and how the acquisition, monitoring, and control of these resources directly impacts schedule, budget, quality, and risk. Expect scenario-based questions where you must identify the correct process or tool for a resource shortage or surplus situation.
Key Points to Remember (for the exam)
- Main Process: Plan Resource Management – performed once or at predefined points in the project
- Key Tools & Techniques: Responsibility assignment matrix, organizational theory, green human resource management, resource-based view, SWOT analysis
- Acquire Resources: Performed periodically throughout the project as needed; failure to acquire necessary resources may affect schedule, budget, customer satisfaction, and quality while increasing risk
- Monitor and Control Resourcing: Performed continuously in all project phases and throughout the project life cycle
- Core Concern: Resources should be assigned and released at the right time, right place, and in the right amount for the project to continue without delays
- Scope: Physical and virtual resources such as equipment, materials, supplies, facilities, infrastructure, software, testing environments, licenses, services
- Team Members: Addressed in the Lead the Team process (not in resource control)
Typical PMI Exam Example
A project manager notices that construction materials are arriving two weeks later than planned, causing delays in three work packages. The project manager reviews the resource usage to date and identifies a shortage of storage space for materials already on-site. According to PMBOK v8, which process should the project manager use to address this situation? The correct answer is Monitor and Control Resourcing, as it is concerned with monitoring resource expenditures and identifying resource shortages and surpluses in a timely manner.
PMI Exam Traps
-
Trap: Confusing Acquire Resources with Monitor and Control Resourcing
- Reality: Acquire Resources is about obtaining the resources; Monitor and Control Resourcing is about tracking usage, identifying shortages/surpluses, and ensuring resources are used and released according to plan
-
Trap: Thinking resource control only applies to team members
- Reality: Monitor and Control Resourcing addresses physical and virtual resources (equipment, materials, supplies, facilities, infrastructure, software, licenses); team members are handled in Lead the Team process
-
Trap: Assuming resource planning is a one-time activity at project start
- Reality: Plan Resource Management is performed once or at predefined points, but Acquire Resources is performed periodically, and Monitor and Control Resourcing is performed continuously
-
Trap: Confusing resource requirements with resource allocations
- Reality: Resource requirements identify types and quantities needed for each work package; resource allocations involve assigning and releasing resources at the right time, right place, and right amount
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Schedule Management | Directly impacted | Insufficient resources affect schedule; resource shortages cause delays |
| Cost Management | Directly impacted | Resource expenditures are monitored; shortages/surpluses affect budget |
| Risk Management | Increased risk | Failure to acquire resources increases risk; worst case = project cancellation |
| Quality Management | Directly impacted | Insufficient resources or capabilities decrease probability of success and affect quality |
Quick Review Questions
-
Which process is concerned with monitoring resource expenditures and identifying resource shortages and surpluses in a timely manner?
-
What are the two main categories of resources addressed in the Monitor and Control Resourcing process?
-
According to PMBOK v8, what are the potential consequences of failing to acquire the necessary resources for a project?
-
Which tools and techniques are used in the Plan Resource Management process?
-
At what frequency should the Monitor and Control Resourcing process be performed?
PMBOK v8 Reference
Section 2.4.2 – Plan Resource Management Section 2.4.3 – Acquire Resources Section 2.4.4 – Monitor and Control Resourcing