Resource Data Information: Schedule Data Components and Supporting Details
PMBOK v8 Definition
Schedule data is the information that describes and supports the schedule. At a minimum, schedule data includes the schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints. Additional supporting detail frequently supplied includes resource requirements by time period (often in the form of a resource histogram), alternative schedules (such as best case or worst case, not-resource-leveled or resource-leveled, or with or without imposed dates), and applied schedule reserves. Schedule data may also include resource histograms, cash flow projections, order and delivery schedules, or other relevant information, as well as schedule forecasts.
Why It Matters for the Exam
Resource data information appears frequently in PMI exam questions testing your understanding of what constitutes schedule data versus other project documents. Questions often ask you to identify which items belong to schedule data, distinguish between schedule data and schedule baseline, or recognize the minimum required components. This concept is tested in both definition-style questions and scenario-based questions where you must determine what information is needed to support a schedule.
Key Points to Remember (for the exam)
- Minimum Required Components: Schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints
- Supporting Detail Examples: Resource requirements by time period (resource histogram), alternative schedules, applied schedule reserves, cash flow projections, order and delivery schedules, schedule forecasts
- Common Format: Resource histogram is the primary format for displaying resource requirements by time period
- Alternative Schedules Types: Best case, worst case, not-resource-leveled, resource-leveled, with imposed dates, without imposed dates
- Schedule Reserves: Applied schedule reserves are part of schedule data, not separate contingency
- Key Distinction: Schedule data supports the schedule but is NOT the schedule baseline itself
- Application Area Variation: The amount of additional data varies by application area
Typical PMI Exam Example
A project manager is developing the project schedule and needs to document supporting information. The team has identified potential resource conflicts and wants to show resource requirements across time periods. Which schedule data component should the project manager use to display this information? Answer: Resource histogram (resource requirements by time period).
PMI Exam Traps
-
Trap: Confusing schedule data with the schedule baseline
-
Reality: Schedule data is the supporting information and documentation; the schedule baseline is the approved version of the schedule model used for comparison
-
Trap: Believing resource histograms are optional
-
Reality: Resource requirements by time period, often in the form of a resource histogram, is a frequently supplied supporting detail
-
Trap: Thinking assumptions and constraints are optional additions
-
Reality: Documentation of all identified assumptions and constraints is a MINIMUM required component of schedule data
-
Trap: Confusing resource calendars with resource histograms
-
Reality: Resource calendars identify working days and shifts when resources are available; resource histograms show resource requirements by time period
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Resource Requirements | Input to Schedule Data | Resource requirements identify types and quantities per work package; these are aggregated and displayed in schedule data |
| Resource Calendar | Complementary Concept | Resource calendars show availability; resource histograms show requirements—both are used together for resource optimization |
| Activity Attributes | Minimum Component | Activity attributes are a required minimum component of schedule data, not optional |
| Schedule Forecasts | Supporting Detail | Schedule forecasts are included in schedule data as supporting detail, not as separate outputs |
Quick Review Questions
-
What are the four minimum required components of schedule data according to PMBOK v8?
-
A project manager needs to document two alternative schedule scenarios—one with resource leveling and one without. Where should these alternative schedules be documented?
-
True or False: Cash flow projections and order delivery schedules are considered schedule data supporting details.
-
What is the primary format used to display resource requirements by time period in schedule data?
-
A project manager has identified assumptions about resource availability and constraints on activity sequencing. Where must these be documented as part of the schedule?
PMBOK v8 Reference
Section 6.5.2.4 - Schedule Data