
Reduce Acceptance Threat: Risk Response Strategy for Low-Priority Threats
PMBOK v8 Definition
Risk acceptance is a risk response strategy that acknowledges the existence of a threat, but no proactive action is taken. This strategy may be appropriate for low-priority threats, and it may also be adopted where it is not possible or cost-effective to address a threat in any other way. Acceptance can be either active or passive; the most common active acceptance strategy is to establish a contingency reserve, including amounts of time, money, or resources to handle the threat if it occurs.
Why It Matters for the Exam
The concept of risk acceptance appears frequently in PMI exam questions testing your ability to distinguish between the seven risk response strategies (avoid, mitigate, transfer, accept, escalate, exploit, enhance, share). Questions often present a scenario where the project team decides to take no proactive action, and you must identify this as acceptance rather than mitigation or avoidance. This concept also appears in questions about contingency reserves and when acceptance is the appropriate choice.
Key Points to Remember (for the exam)
- Definition Core: Risk acceptance means acknowledging the threat exists but taking no proactive action unless the threat occurs
- When to Use: Appropriate for low-priority threats OR when it is not possible or cost-effective to address the threat in any other way
- Two Types: Active acceptance (establish contingency reserve of time, money, or resources) vs. Passive acceptance (no action, deal with it if it happens)
- Key Output: The most common active acceptance strategy is establishing a contingency reserve
- Common Confusion: Acceptance is NOT the same as mitigation—mitigation takes action to reduce probability/impact; acceptance takes no proactive action
- Exam Trap: Acceptance does NOT mean ignoring the risk—it means documenting it in the risk register and acknowledging it exists
- Relationship to Overall Project Risk: When no proactive response strategy is possible for overall project risk, the organization may choose acceptance even if risk is outside agreed-upon thresholds
Typical PMI Exam Example
A project manager identifies a threat that has a 5% probability of causing a minor delay worth $500. The cost to implement a mitigation strategy would be $2,000. The project team decides to document the risk but take no proactive action. Which risk response strategy is being used?
Answer: Risk acceptance (passive acceptance), because the team acknowledges the threat but takes no proactive action, and the cost to address it exceeds the potential impact.
PMI Exam Traps
-
Trap: Confusing acceptance with mitigation when a contingency reserve is established
- Reality: Contingency reserve is an active acceptance strategy—you accept the risk might occur and set aside resources to handle it if it does. Mitigation takes action to reduce probability or impact before the risk occurs.
-
Trap: Thinking acceptance means the risk is ignored or not documented
- Reality: Acceptance requires documenting the risk in the risk register and acknowledging its existence. The team simply chooses not to take proactive action.
-
Trap: Confusing acceptance with transference
- Reality: Transference shifts ownership/liability to another party (insurance, bonds, warranties). Acceptance keeps the risk with the project team but takes no proactive action.
-
Trap: Assuming acceptance is only for negative risks (threats)
- Reality: Acceptance can apply to both threats (negative risks) and opportunities (positive risks). For overall project risk, acceptance may be chosen even when risk is outside agreed-upon thresholds.
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Risk Mitigation | Opposing strategy | Mitigation reduces probability/impact; acceptance takes no proactive action |
| Contingency Reserve | Output of active acceptance | The most common active acceptance strategy; tested as a key tool |
| Risk Register | Document where acceptance is recorded | All accepted risks must be documented in the risk register |
| Overall Project Risk | Application of acceptance | Acceptance may be used when no proactive response is possible for overall project risk |
Quick Review Questions
-
A project team identifies a threat with very low probability and low impact. They decide to document it but take no action unless it occurs. Which risk response strategy is this?
-
What is the difference between active acceptance and passive acceptance?
-
When is risk acceptance the appropriate strategy even for threats that are not low-priority?
-
A project manager establishes a contingency reserve of $10,000 for a potential threat. Is this risk mitigation or risk acceptance? Why?
-
True or False: Risk acceptance means the project team ignores the risk and does not document it.
PMBOK v8 Reference
Section 11.5 - Plan Risk Responses (Risk Acceptance strategy within Threat Response Strategies)