
Project Team Chart: Graphical Display of Reporting Relationships
PMBOK v8 Definition
A project organization chart is a graphical display of project team members and their reporting relationships. The chart can be formal or informal, highly detailed or broadly framed, based on the needs of the project. It documents team members and their reporting relationships, providing guidance on how the project team resources should be defined, staffed, managed, and eventually released.
Why It Matters for the Exam
The Project Team Chart appears frequently in PMI exam questions related to Resource Management, particularly when testing your understanding of organizational structures and team documentation. Questions often ask you to distinguish between the project organization chart and other charts (WBS, RACI), or to identify when a formal versus informal chart is appropriate based on project size and complexity.
Key Points to Remember (for the exam)
- Main Purpose: Graphical display of project team members AND their reporting relationships
- Flexibility Principle: Can be formal or informal, highly detailed or broadly framed—depends on project needs
- Scale Example: A 3,000-person disaster response team requires greater detail than a 20-person internal project
- Key Distinction: Shows WHO reports to WHOM (reporting structure), NOT who does what work (that is RACI)
- Hierarchical Charts: Traditional top-down format showing positions and relationships; WBS is a related hierarchical chart
- Location: Part of the Resource Management Plan, specifically under project team resource management guidance
- Related Elements: Also used in Risk Management planning (timing and funding protocols)
Typical PMI Exam Example
A project manager is developing documentation for a 50-person software development project. The sponsor asks for a visual representation of who reports to whom on the project team. Which document should the project manager create?
Answer: A project organization chart (hierarchical chart showing reporting relationships).
PMI Exam Traps
-
Trap: Confusing the project organization chart with the Work Breakdown Structure (WBS)
- Reality: The project organization chart shows team members and reporting relationships; the WBS shows deliverables and work packages
-
Trap: Thinking the chart must always be formal and highly detailed
- Reality: The chart can be formal or informal, detailed or broad—it depends on project needs and size
-
Trap: Assuming the chart defines roles and responsibilities
- Reality: The chart shows reporting relationships; role definitions come from other documents (RACI matrix, role descriptions)
-
Trap: Believing the chart is only created once at project initiation
- Reality: Resource control includes methods for ensuring resources are available as needed; the chart may be updated as team composition changes
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Work Breakdown Structure (WBS) | Both are hierarchical charts | WBS shows deliverables; project organization chart shows people and reporting lines |
| Resource Management Plan | Contains the chart | Chart is part of how resources are defined, staffed, managed, and released |
| RACI Matrix | Complements the chart | Chart shows reporting; RACI shows responsibilities for specific work |
| Team Charter / Ground Rules | Related documentation | Ground rules set expected behavior; chart shows who is on the team |
| Risk Management Plan | Uses project organization charts | Charts identify who performs risk processes and reporting for risk activities |
Quick Review Questions
-
A project has 3,000 team members responding to a disaster. Should the project organization chart be highly detailed or broadly framed?
-
What is the exact PMBOK v8 definition of a project organization chart?
-
A project manager creates a graphical, top-down display showing positions and reporting relationships. What type of chart is this?
-
True or False: The project organization chart is always formal and cannot be informal.
-
What is the difference between a project organization chart and a Work Breakdown Structure?
PMBOK v8 Reference
Section 5.2.3.1 - Project Organization Charts