Log Member: Stakeholder Identification and Classification in
PMBOK v8 Definition
A log member refers to an entry within the Stakeholder Register, which is a project document that captures identification and assessment information about project stakeholders. The Stakeholder Register includes identification information (name, organizational position, location, contact details, and role on the project), assessment information (major requirements, expectations, potential for influencing project outcomes, and the phase where the stakeholder has the most influence or impact), and stakeholder classification (internal/external, impact/influence/power/interest, upward/downward/outward/sideward, or any other classification model chosen by the project manager). This document is an input to the Plan Stakeholder Engagement process.
Why It Matters for the Exam
The Stakeholder Register and its log members are frequently tested because they appear as inputs to multiple processes, including Plan Stakeholder Engagement and Implement Risk Responses. PMI exam questions often test your ability to identify which information belongs in the Stakeholder Register versus other project documents, and how classification models (power/interest grid, influence/impact) determine engagement strategies.
Key Points to Remember (for the exam)
- Main Input To: Plan Stakeholder Engagement process (Project documents input)
- Three Data Categories: Identification information, Assessment information, Stakeholder classification
- Classification Models Tested: Internal/external, impact/influence/power/interest, upward/downward/outward/sideward
- Key Assessment Element: "Phase of the project life cycle where the stakeholder has the most influence or impact"
- Common Confusion: Do not confuse the Stakeholder Register (log members) with the Stakeholder Engagement Plan (which is the output of Plan Stakeholder Engagement)
- Output Usage: The Stakeholder Register feeds into the Risk Register and Risk Report during Implement Risk Responses
Typical PMI Exam Example
A project manager is developing a stakeholder engagement plan for a construction project. The project sponsor has high power and high interest. The project manager needs to classify this stakeholder to determine the appropriate engagement approach. Question: Which document contains the stakeholder classification information needed for this analysis? Answer: The Stakeholder Register (log members with classification data).
PMI Exam Traps
-
Trap: Confusing the Stakeholder Register with the Stakeholder Engagement Plan
- Reality: The Stakeholder Register contains identification and classification data; the Stakeholder Engagement Plan contains the actionable strategies for interacting with stakeholders
-
Trap: Thinking stakeholder classification is optional or only one model exists
- Reality: PMBOK v8 lists multiple classification models (power/interest, influence/impact, upward/downward/outward/sideward) and the project manager chooses the appropriate model
-
Trap: Assuming the Stakeholder Register is a one-time creation
- Reality: Plan Stakeholder Engagement is "performed periodically throughout the project as needed"
-
Trap: Confusing assessment information with identification information
- Reality: Assessment includes requirements, expectations, influence potential, and phase of maximum impact—NOT just name and contact details
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Plan Stakeholder Engagement | Input to process | Stakeholder Register is a direct input; changes to log members trigger updates to the engagement plan |
| Implement Risk Responses | Input to process | Stakeholder Register and Risk Register share information; stakeholders influence risk responses |
| Communications Management Plan | Related planning document | Stakeholder classification determines communication channels and frequency |
| Risk Register | Complementary document | Stakeholder log members feed into risk identification and assessment |
Quick Review Questions
-
What three categories of information are captured for each log member in the Stakeholder Register?
-
A stakeholder has high influence but low interest. Which classification model would capture this distinction?
-
During which process is the Stakeholder Register used as an input to develop an actionable engagement plan?
-
True or False: The Stakeholder Register is created once at project initiation and never updated.
-
What specific assessment information about a stakeholder relates to "the phase of the project life cycle where the stakeholder has the most influence or impact"?
PMBOK v8 Reference
Section 4 – Inputs and Outputs (Page 141-142) – Stakeholder Register content and structure
Section 2.5 – Stakeholder Performance Domain (Pages 71-77) – Stakeholder engagement planning and interactions