For example, the financial management plan may: Define the points in the WBS at which meas…
PMBOK v8 Definition
The financial management plan is a component of the program or project management plan that describes how costs will be planned, structured, and controlled. It documents the financial management processes and their associated tools and techniques. The financial management plan may define the points in the Work Breakdown Structure (WBS) at which measurement of control accounts will be performed, establish the Earned Value Management (EVM) techniques to be employed (e.g., weighted milestones, fixed formula, percent complete), and specify tracking methodologies and EVM computation equations for calculating projected estimate at completion (EAC) forecasts.
Why It Matters for the Exam
The financial management plan is frequently tested because it connects cost management with scope management through the WBS and control accounts. Exam questions commonly ask what the financial management plan establishes, particularly the EVM techniques and WBS measurement points, and how it differs from other cost management documents. Expect situational questions where you must identify which document defines control account measurement points.
Key Points to Remember (for the exam)
- Main Purpose: Describes how costs will be planned, structured, and controlled
- WBS Integration: Defines specific WBS points where control account measurement occurs
- EVM Techniques: Establishes methods like weighted milestones, fixed formula, and percent complete
- EAC Forecasting: Specifies computation equations for calculating projected estimate at completion (EAC) forecasts
- Reporting Formats: Defines formats and frequency for various cost reports
- Strategic Funding: Includes description of strategic funding choices
- Currency Procedures: Contains procedures for accounting for fluctuations in currency exchange rates
- Cost Recording: Documents procedures for project cost recording
- Common Confusion: Do not confuse with the cost baseline (which is the authorized budget) or the scope baseline (which contains the WBS itself)
Typical PMI Exam Example
A project manager is developing the financial management plan. The project involves multiple work packages with varying complexity. The project manager needs to define how cost performance will be measured at different WBS levels. Which element should the financial management plan establish? Answer: The points in the WBS at which measurement of control accounts will be performed, and the EVM techniques to be employed.
PMI Exam Traps
-
Trap: Confusing the financial management plan with the cost baseline
-
Reality: The financial management plan describes how costs are managed and controlled; the cost baseline is the authorized budget itself
-
Trap: Thinking EVM techniques are defined in the scope management plan
-
Reality: EVM techniques (weighted milestones, fixed formula, percent complete) are established in the financial management plan
-
Trap: Assuming control account measurement points are defined in the WBS dictionary
-
Reality: The WBS dictionary describes the WBS components; the financial management plan defines where measurement of control accounts will be performed within the WBS
-
Trap: Believing the financial management plan only contains cost information
-
Reality: It also includes strategic funding choices, currency exchange procedures, and cost recording procedures
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Work Breakdown Structure (WBS) | Defines measurement points | Financial management plan identifies WBS points for control account measurement |
| Control Accounts | Measurement application | Control accounts are where EVM performance measurement occurs |
| Earned Value Management (EVM) | Techniques established | EVM techniques (weighted milestones, fixed formula, percent complete) are specified in the financial management plan |
| Estimate at Completion (EAC) | Forecasting equations | Financial management plan specifies equations for calculating projected EAC forecasts |
| Performance Measurement Baseline (PMB) | Budget reference | Total of planned value (PV) is the PMB; financial management plan defines how it is measured |
Quick Review Questions
-
Which document defines the points in the WBS at which measurement of control accounts will be performed?
-
What EVM techniques can be established in the financial management plan? (Name at least three)
-
What is the difference between the financial management plan and the cost baseline?
-
What additional details beyond cost management are included in the financial management plan?
-
How does the financial management plan relate to the Estimate at Completion (EAC)?
PMBOK v8 Reference
Section 4 – Inputs and Outputs (Financial Management Plan content described in the context of cost management and EVM rules of performance measurement)