Enterprise Environmental Factors: Internal and External Influences
PMBOK v8 Definition
Enterprise environmental factors (EEFs) refer to conditions not directly influenced by the project team that impact, constrain, or direct the project. These conditions can be internal and/or external to the organization. EEFs are considered as inputs to many project management processes, specifically for most planning processes, and can either enhance or constrain project management options as well as influence tailoring needs and project outcomes, positively or negatively.
Why It Matters for the Exam
EEFs appear frequently on the PMI exam because they are inputs to nearly all planning processes. Questions test your ability to distinguish EEFs from organizational process assets (OPAs) and to recognize which factors are internal versus external to the organization. Expect situational questions where you must identify whether a given condition is an EEF or OPA.
Key Points to Remember (for the exam)
- Definition: Conditions that impact, constrain, or direct the project; not directly influenced by the project team
- Two Categories: Internal to the organization AND external to the organization
- Impact Type: Can be positive, negative, or neutral on project characteristics, stakeholders, or project teams
- Process Input: Input to most planning processes specifically
- Key Differentiator: EEFs are OUTSIDE the project team's control; OPAs are internal assets the team can use
- Internal EEF Examples: Organizational culture, structure, governance, geographic distribution of facilities and resources
- External EEF Examples: Marketplace conditions, legal restrictions, government/industry standards, financial considerations, physical environmental elements
Typical PMI Exam Example
A project manager is developing the project management plan for a construction project in a new country. The country has strict environmental regulations and a volatile currency exchange rate. The project manager documents these conditions as enterprise environmental factors because they are external to the organization and cannot be directly influenced by the project team.
PMI Exam Traps
-
Trap: Confusing EEFs with OPAs when both are mentioned in the same question
- Reality: EEFs are conditions that constrain or influence the project (external or internal but outside team control); OPAs are policies, procedures, and knowledge bases the team can use
-
Trap: Thinking all EEFs are negative constraints
- Reality: EEFs can enhance OR constrain project management options and influence outcomes positively or negatively
-
Trap: Assuming internal EEFs are the same as OPAs
- Reality: Internal EEFs (culture, structure, geographic distribution) are conditions the team cannot change; OPAs (templates, policies, historical information) are assets the team can actively use
-
Trap: Forgetting EEFs are inputs to planning processes only
- Reality: EEFs are inputs to most planning processes, but also influence tailoring needs and project outcomes throughout the project
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Organizational Process Assets (OPAs) | Complements | Both are project influences; EEFs = external/internal conditions; OPAs = internal assets |
| Project Management Plan | Input to | EEFs are inputs to developing the project management plan |
| Tailoring | Influences | EEFs influence tailoring needs and project outcomes |
| Organizational Culture | Internal EEF | Culture, structure, and governance are internal EEFs that impact project execution |
Quick Review Questions
-
A project is being initiated in an organization with a hierarchical structure and strong cultural norms. Are these conditions EEFs or OPAs?
-
During planning, the project team identifies competitor activities and new government regulations. How should these be classified in the project documents?
-
What is the key difference between enterprise environmental factors and organizational process assets regarding the project team's ability to influence them?
-
A project manager is selecting a project management methodology. Which category of project influences would include marketplace conditions and legal restrictions?
-
Can enterprise environmental factors have a positive impact on project outcomes, or are they always constraints?
PMBOK v8 Reference
Section 2.2.1 - Enterprise Environmental Factors Section 2.2.1.1 - Enterprise Environmental Factors Internal to the Organization Section 2.2.1.2 - Enterprise Environmental Factors External to the Organization