Conducted Progress Postmortems: Continuous Improvement During Project Life Cycle
PMBOK v8 Definition
An in-progress postmortem is a structured process conducted at various stages of the project life cycle to analyze current performance, identify issues, and implement improvements. Unlike traditional postmortems held at the end of a project, these reviews are conducted periodically to ensure continuous improvement and timely problem-solving. This concept belongs to the Executing and Monitoring and Controlling performance domains.
Why It Matters for the Exam
The PMI exam frequently tests the distinction between in-progress postmortems and traditional end-of-project retrospectives, as this reflects modern agile and adaptive project management approaches. Questions often appear in scenario-based items where a project manager needs to decide when to conduct performance reviews or how to implement continuous improvement during the project life cycle.
Key Points to Remember (for the exam)
- Primary Purpose: Analyze current performance, identify issues, and implement improvements during the project life cycle (not after project completion)
- Timing: Conducted at various stages/periodically throughout the project, not only at the end
- Key Difference from Traditional Postmortems: Traditional postmortems occur at project end; in-progress postmortems occur continuously during execution
- Main Output: Actionable improvements and timely problem-solving for current project phases
- Key Tool: Information radiator (Figure 5-9) to visualize findings and promote awareness
- Common Confusion: Do not confuse in-progress postmortems with inspections—inspections examine work product conformance to standards; postmortems analyze overall performance and processes
- Relationship to Retrospectives: In-progress postmortems align with iteration retrospectives but are broader, covering the entire project life cycle
Typical PMI Exam Example
A project manager is halfway through a 12-month software development project. The team has noticed recurring delays in testing phases. The project manager decides to conduct a structured review of current performance to identify root causes and implement corrective actions immediately. This is an example of an in-progress postmortem.
PMI Exam Traps
-
Trap: Confusing in-progress postmortems with end-of-project retrospectives
-
Reality: In-progress postmortems occur during the project; retrospectives can occur at iteration/release end or project close
-
Trap: Believing postmortems only happen at project closure
-
Reality: PMBOK v8 explicitly describes in-progress postmortems conducted at various stages for continuous improvement
-
Trap: Mixing up inspections with in-progress postmortems
-
Reality: Inspections examine work product conformance to documented standards; postmortems analyze performance and processes
-
Trap: Thinking in-progress postmortems are only for agile projects
-
Reality: PMBOK v8 describes them as applicable across the project life cycle, regardless of methodology
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Information Radiator | Key Tool | Visualizes postmortem findings; promotes awareness and decisions (Figure 5-9) |
| Retrospectives | Complementary Process | Both capture lessons learned; retrospectives focus on iterations/releases |
| Inspections | Different Process | Inspections check conformance to standards; postmortems analyze performance |
| Close Project or Phase | Sequential Activity | Knowledge transfer and final retrospectives occur during project/phase closure |
Quick Review Questions
-
What is the primary difference between an in-progress postmortem and a traditional postmortem?
-
During which performance domain(s) would a project manager typically conduct an in-progress postmortem?
-
A project team is examining a completed deliverable to verify it meets documented standards. Is this an in-progress postmortem or an inspection?
-
What tool, referenced in Figure 5-9, helps visualize in-progress postmortem findings?
-
How do in-progress postmortems support continuous improvement during the project life cycle?
PMBOK v8 Reference
Section 5.2.2 - Information Radiator (Figure 5-9) Section 2.1 - Performance Domain Processes (Table 2-1) Section 2.1.6 - Close Project or Phase (knowledge transfer and retrospectives)