18 Project Influences: Enterprise Environmental Factors and Organizational Process Assets
PMBOK v8 Definition
Enterprise environmental factors (EEFs) refer to conditions not directly influenced by the project team that impact, constrain, or direct the project. These conditions can be internal and/or external to the organization. Organizational process assets (OPAs) are internal to the organization and may arise from the organization itself, a portfolio, a program, another project, or a combination of these. Together, EEFs and OPAs constitute the two categories of project influences that affect how projects are managed and executed.
Why It Matters for the Exam
This concept appears in approximately 15-20% of PMI exam questions, particularly in scenario-based questions where you must identify whether a given factor is an EEF or an OPA. The exam frequently tests your ability to distinguish between these two categories and understand which processes use them as inputs. Questions often present real-world situations requiring you to classify organizational factors correctly.
Key Points to Remember (for the exam)
-
EEFs are external or internal conditions that the project team cannot directly control. They enhance or constrain project management options and influence tailoring needs and project outcomes, positively or negatively.
-
OPAs are internal to the organization and include processes, policies, procedures, and organizational knowledge repositories. They come from the organization, portfolio, program, or other projects.
-
Internal EEFs include: organizational culture, structure, governance, geographic distribution of facilities and resources, infrastructure, and information technology software.
-
External EEFs include: market conditions, legal restrictions, industry standards, and governmental regulations.
-
Common Confusion: Many candidates confuse internal EEFs with OPAs. Remember: EEFs are conditions not directly influenced by the project team, while OPAs are assets the team can use and update.
-
Key Input: EEFs and OPAs are inputs to most planning processes. They must be considered if the project is to be effective.
-
Tailoring Impact: EEFs influence tailoring needs and project outcomes. OPAs provide historical information and standardized processes for tailoring decisions.
Typical PMI Exam Example
A project manager is developing the project management plan for a new software development project. The organization has a standardized template for project charters and lessons learned from three previous similar projects. Which category of project influence does this represent?
Answer: Organizational process assets (OPAs), specifically processes, policies, and procedures from the organizational knowledge repository.
PMI Exam Traps
-
Trap: Confusing internal EEFs with OPAs because both are internal to the organization. Reality: EEFs are conditions the team cannot control (e.g., organizational culture); OPAs are assets the team can use (e.g., templates, policies).
-
Trap: Thinking all external factors are EEFs and all internal factors are OPAs. Reality: EEFs can be internal (e.g., organizational culture, infrastructure) or external (e.g., market conditions). OPAs are always internal.
-
Trap: Believing OPAs only come from the current project. Reality: OPAs may arise from the organization, a portfolio, a program, another project, or a combination of these.
-
Trap: Confusing project team influence over EEFs. Reality: EEFs are conditions not directly influenced by the project team. The team cannot change organizational culture or legal regulations.
Important PMI Connections
| Related Concept | Relationship Type | Exam Attention Point |
|---|---|---|
| Organizational Knowledge Repository | Component of OPAs | Contains processes, policies, and procedures from past projects |
| Tailoring | Influenced by EEFs and OPAs | EEFs constrain options; OPAs provide historical guidance |
| Project Management Plan Development | Input | EEFs and OPAs are critical inputs to planning processes |
| Organizational Structure | Internal EEF | Impacts authority, communication, and decision-making |
Quick Review Questions
-
A project team discovers that the organization's IT infrastructure cannot support the proposed cloud-based solution. Is this an EEF or an OPA?
-
The project manager uses a standardized risk register template from a previous project. Which category of project influence does this represent?
-
During planning, the team considers the organization's culture of hierarchical decision-making. Is this an internal EEF or an OPA?
-
Government regulations require environmental impact assessments for all construction projects. How should this be classified in terms of project influences?
-
A project team updates the lessons learned repository after project completion. Does this action modify EEFs or OPAs?
PMBOK v8 Reference
Section 2.2 – Project Influences (Figure 2-4) Section 2.2.1 – Enterprise Environmental Factors